streber/Milestones

Milestones

Tasks openAssigned to
v0.094 - refactor query filters

-
2.4 days required
19 closed / 45 open
v0.095 - make use of filters in GUI
Since we implemented new query filters in v0.074 we should use this queries for refining some lists like project History, project Changes and Persons.

-
4.965 days required
4 closed / 28 open
v0.10 - getting stable-
3.82 weeks required
v0.12 - wiki editing-
v0.13 - ajax forms-
1.9 days required
v0.14 - ajax lists-
2.66 weeks required
v0.15 - inplace editing

-
1.24 weeks required
0 closed / 3 open
v0.19 - ajax tuning-
2 weeks required
v0.20 - ajax interface
This version will conclude the interface rebuild.

Like v0.10 it will be considered a "stable version" and will be updated and maintened until v0.30 is been released. Also see release versions.


-
0 closed / 1 open
v0.25 - getting in & out
  • add import and export of projects as xml
  • probably add importer for netoffice and mantis

-
3.5 days required
0 closed / 1 open
v0.3- timing tasks
With this version we refacture some of the task timing functionality, like
  • rolling out tasks in gantt like diagrams
  • using task dependency
  • summing up tasks for projects, milestones and task folders

-
2.525 days required
4 closed / 12 open
v2.0 - far far away
In this milestone, we collect features that would be really cool, but are also a lot of work and are not following the main focus of streber.

Apr 2, 2009
(1939 days late)
1.88 weeks required
3 closed / 11 open
vX - unlikely
This milestone collects feature requests which are not planned, unclear or rejected.

-
0 closed / 2 open