Bug

Tasks - Selecting Planned Start date fills in Planned End date

Summary

open
Jan 10, 2006
4 hours ... 10 hours
Jan 10, 2006 / guest
Jan 5, 2009 / phsouzacruz
 

Attached files

No files uploaded
 
This task does not have any text yet.
Doubleclick here to add some.

5 Comments

pixtur:Could not be preproduced

12 years ago

more details needed.

guest:Reply to Could not be preproduced

12 years ago -

When creating a new task, or updating a task.

Enter a start date. Return to the main task tree of the project, and you will see that the due date will be the start date you just entered.

guest:Reply to Could not be preproduced

12 years ago (5. update 11 years ago) -

Just try to edit this task/bug. Click on the calendar for \'Start date\', and choose a date. The date will appear in the \'Planned End date\' field.

It does not always work. Just keep clicking on the calendar icon and selecting a date, and it will happen. It took me 4 time to make it happen.

I\'m using IE6.0 and this version of Streber.

pixtur:Confirmed

12 years ago (2. update 11 years ago)

I could reproduced it immediately with IE6. Not sure what causes this weird behaviour and will check the javascript functions to get a clue. Thank you very much for pointing out.

tom




madlyr:Some more info #2815